Construction Updates
Track the progress of Project 2025!
- Construction Update - December 2024
- Construction Update - October 2024
- Construction Update - July 2024
- Construction Update - April 2024
- Construction Update - February 2024
Construction Update - December 2024
Updated Timelapse Video
Time Lapse Photography donated by Live Patrol – Daniel Carloni ‘07
First Interior Look Video
Get your first glimpse at the interior of our new dining hall and theatre.
Time Lapse Photography donated by Live Patrol – Daniel Carloni ‘07
Building the Future Together
Construction Update - December 2024
We’re Making Great Progress!
We’re thrilled to announce that Project 2025 is moving along right on schedule! With the building now fully enclosed for the winter, our focus has shifted to interior work. Since our last update in October, significant progress has been made, including:
- Pre-cast wall staining completed – The color looks fantastic!
- Roofing work 99% completed
- Punch windows and curtain wall Completed
- Theatre steel deck completed
- Theatre seating topping completed
- Theatre seat site measurements to begin seat production completed – Have you picked your seat?
- Interior framing in progress
As we approach 2025, we’re excited to share more updates on the interior progress and the latest construction developments. We’re making great strides, and your continued support has been instrumental every step of the way. Together, we can build on this strong foundation. I invite you to join us in furthering this mission by making a gift today—visit our Building the Future Together page to contribute.
We are thrilled to officially announce the name of the new VC store: The Leslie Balsamo Armoury. The store will be relocated to the ground floor of the new addition. A heartfelt thank you to the Balsamo family for their generous support and to Mrs. Balsamo for her dedication to making the Armoury the go-to destination for spirit wear over the years.
Thank you for being an integral part of the Villanova community and for walking this journey with us. We also extend our deepest gratitude to our donors and benefactors whose leadership and generosity have paved the way.
Thank you to the following benefactors who have added their names to our donor wall with their leadership donation.
Presenting Sponsors for VC Musical Productions & Science Lab, Main Floor - Contento Family
Science Lab, Main Floor - Zancor Homes
Upper School Classroom - Téa Fusco ’24 & Family
These donors join those who have already taken the opportunity to make a difference in our school's future, listed below:
Athletic Centre – Gurizzan Family
Dining Hall/Kitchen – Gurizzan Family
Sr. Student Lounge – Mikhael Family
The Armoury – Balsamo Family
Vending Area – Cortellucci-Fiuza Family
Visual Arts Studio – Zanetti Family
Classroom – Tatone – Haces Family
Visual Arts Studio – Zanetti Family
Projection Room – Williams & Partners
Construction Update - October 2024
Time Lapse Photography donated by Live Patrol – Daniel Carloni ‘07
Drone Footage of Project 2025 Progress
Watch Artist Renderings Come to Life
Building the Future Together
Construction Update - October 2024
The wonderful summer weather allowed for significant progress to be made as Project 2025 takes shape and the outer envelope is being completed in order to prepare for interior work and finishing to take place over the winter months.
As of September 15th, this progress has included:
- Structural steel completed
- South athletic centre entrance completed
- Stone bedding for ground level slab-on-grade completed
- Slab-on-grade concrete work completed
- Second floor coreslab work completed
- Blockwork for stairwell and elevator completed
- Elevator installation commenced
- Pre-cast cladding on south, east and north (theatre, dining hall, entrance) in place
Thank you to the following families for continuing to support our mission and our vision for VC through their generosity and contributions to Project 2025.
Athletic Centre – Gurizzan Family
Dining Hall/Kitchen – Gurizzan Family
Sr. Student Lounge – Mikhael Family
The Armoury – Balsamo Family
Vending Area – Cortellucci-Fiuza Family
Classroom – Tatone – Haces Family
Visual Arts Studio – Zanetti Family
Projection Room – Williams & Partners
Suspended Floor Slab for Second Floor
Removal of Precast Wall at South Entrance
Construction Update - July 2024
Building the Future Together
Construction Update - July 2024
Our campus remains busier than ever as Project 2025 continues to move forward reaching some important milestones.
As of July 15th, this progress has included:
- Removal of the precast wall at south entrance
- Installation of steel beam and canopy steel at south entrance
- Installation of stud work at roof and middle of curtain wall
- Hollow core sab at second level
- Structural steel installation - Phase 02 columns and beams
- Installation of roof deck for Phase 01
Suspended Floor Slab for Second Floor
Removal of Precast Wall at South Entrance
Construction Update - April 2024
Building the Future Together
Construction Update - April 2024
We continue to make good progress as evidenced by the latest time lapse footage captured in the video above. Since our last update we are happy to report that the south and east foundation walls and ground floor slab are now complete and steel columns are in place. We look forward to sharing our next update as we track Project 2025's progress out of the ground. Here We Grow Again!
South and East Foundation Walls
Interior View of Future Fitness Room
Construction Update - February 2024
Building the Future Together
Construction Update - February 2024
Project 2025 has seen a great deal of progress in January and February, and we are excited to show you the work that has been done through the time lapse photography (above) and photos (below).
The weather has certainly enabled construction to move quickly with the milder winter we have experienced this year. When work first began in November, the construction site changed a great deal. We have had no construction delays to date, and we are pleased to share this update with you.
-
Demolition Completion – 1st mobilization: December 15, 2023
-
Demolition Completion – 2nd mobilization (South Athletic Centre wall): January 30, 2024
-
Bulk Excavation of Basement Area Start Date: January 08, 2024
-
Bulk Excavation of Basement Area Completion Date: January 22, 2024
-
Forming Contractor Mobilization Date: January 31, 2024
-
Concrete Footings Start Date: February 01, 2024
Thank you to our project management team, Accel, our consultants and trades who are working with us to make our vision for your children come to fruition.
Stay tuned for more construction updates as the building rises out of the ground and along with updates on our fundraising efforts. Thank you to all who have supported the Building the Future Together Campaign. Donations can be made or pledged over the next one, two or three years. If you would like to know how you can do so or have questions about naming opportunities, please contact Mr. Paradiso at pjparadiso@villanovacollege.com or members of the Executive Campaign Committee. If you would like to join the Executive Campaign Committee, please contact Mr. Paradiso.
We are VC. GO KNIGHTS! GO BLUE!
Executive Campaign Committee Members
Co-Chairs – Danny and Marina Gurizzan
Nick Creatura
Elya Ornelas ‘03
Michael D’Angelo ‘05
Gennaro Di Santo – Ex-Officio – Chair of the Board